BQE Restarts Selenium Treatment Plant Operations at Kemess Project
What happened
BQE announced the successful restart and operation of the selenium removal treatment plant at the Kemess Project, which is undertaken in collaboration with Centerra Gold Inc. The facility utilizes BQE's patented Selen-IX process. Commissioning activities began in late summer of 2026, and seasonal operations commenced. Official tests received as of September 14, 2026, confirmed that selenium concentrations in the effluent were below the detection limit of less than 2 parts per billion.
From finanznachrichten.de
Why it matters
The operational restart is part of the larger development plans for the Kemess Project. The successful operation of the full-scale plant demonstrates the viability of the Selen-IX technology for this specific application.
From finanznachrichten.de
Who's involved
Keep exploring
The entities involved
-
David Kratochvil
Czech paralympic swimmer
Nothing else this week.