Propel NY Energy Seeks Permits for $3.26 Billion Power Line Expansion
The latest in this situation
- LS Cable & System and Taihan Cable & Solution were selected as cable suppliers for the Propel NY Energy transmission project linking Long Island with NYC.
- North Shore Central and Garden City school districts filed legal petitions and raised concerns regarding the Propel NY Energy transmission project.
- Consolidated Edison is building substations in NYC to meet rising demand driven by electrification.
- Propel NY Energy received key regulatory approval for a project addressing Long Island's grid shortfall.
- Sea Cliff submitted a report on project damage, while the Department of Public Service issued a water quality certificate for the Propel project.
How it started
What happened
Propel NY Energy, a $3.26 billion project involving a 90-mile series of power lines, is seeking permits from the U.S. Army Corps of Engineers. The project, which runs from western Suffolk to Westchester, has received three pre-construction contracts awarded by the New York Power Authority and New York Transco to local firms. Despite support from state agencies and utilities, the project faces fierce opposition from local towns and three school districts.
From newsday.com
Why it matters
The project represents a major critical infrastructure upgrade to the electric grid in New York State. The awarding of pre-construction contracts to local firms indicates immediate economic activity in preparation for the power line construction.
From newsday.com
Who's involved
- HempsteadVillage in North Shore communities where much of the power line work will take place
Who could feel it
Possible knock-on effectsThese are possibilities Brind reasoned out, not predictions, and not advice. Most are not stated in any report.
- HempsteadSpeculative
The community might face increased costs related to ratepayer bills due to the infrastructure project.
Possible ripples
Who this could reach next, traced step by step from the reporting. Possibilities worth considering, not forecasts.How it developed
Newest first. Tap a step to see who reported it.- North Shore Central and Garden City school districts filed legal petitions and raised concerns regarding the Propel NY Energy transmission project.Sub-event
- Sea Cliff submitted a report on project damage, while the Department of Public Service issued a water quality certificate for the Propel project.Sub-event
- A critical infrastructure upgrade to the electric grid is underway in New York State.Sub-event
Propel NY Energy project seeks Army Corps permits for work impacting NY Power Authority and Hempstead.1 source