Prologis Sues Trenton Over Voter-Approved Data Center Ban
What happened
Prologis filed a federal lawsuit against the city of Trenton on November 19, 2026. The suit challenges a charter amendment approved by Trenton voters that prohibits the construction of data centers larger than 25 megawatts within city limits. Prologis argues that this ban is unconstitutional and cannot be applied to its under-construction data center project. A group of Trenton residents is seeking to join the legal action.
From wvxu.org
Why it matters
The lawsuit directly challenges the regulatory framework governing large-scale data center construction in Trenton. The legal action questions the validity of the city's voter-approved limits, which affects the future of the controversial Project Mila.
The conflict centers on Project Mila, a controversial data center project involving Prologis and Trenton.
From wvxu.org