Mississauga Council Passes Interim Control By-law Affecting Digital Infrastructure Land…
What happened
The Council of the City of Mississauga passed By-law 0143-2026, the Interim Control By-law, on September 16, 2026. The by-law introduces a control on specific lands within the city, pending a review of Mississauga Official Plan policies and zoning regulations. This control specifically targets the use of these lands for Major Digital Infrastructure Facility use requiring 10 megawatts or greater in total peak power demand.
From mississauga.com
Why it matters
The Interim Control By-law is effective for a period of one year from the date of passing, though the Council has the authority to extend it for up to two years. Affected parties wishing to appeal the by-law have until November 5, 2026, to file through the Ontario Land Tribunal.